Knowing the importance of this bridge to so many, the City has developed an ambitious schedule.  Here are current milestone dates, with a continuous public process throughout.

Summer - Winter 2018 - Develop design options

Spring 2019 – Choose preferred alternative

Summer 2019 - Begin final design of preferred alternative

Fall 2019 – Complete 25% design and begin permitting process

Fall 2020 - Complete final design and advertise for construction

2022 - Project completion

See the News and Meetings page for a schedule of public meetings and Task Force meetings.